Almond Grove Project

This page has been created to provide regular updates to the residents about the progress of the Almond Grove Street Rehabilitation Project.  We encourage interested parties to subscribe to the “NOTIFY ME” service located on the left hand side of this page in order to be notified immediately each time the project page is updated.

Construction Update on Almond Grove Phase I – Broadway and Bachman Avenue


Resident and business owner pre-construction meetings were held on April 25th and April 26th to discuss the upcoming construction with the residents and business owners on Broadway, Clifton Avenue, and Bachman Avenue who will be directly impacted the by construction work.  The agenda and presentation slides for those meetings can be viewed by clicking on the links below.
A list of Frequently Asked Questions resulting from the meeting and regarding the construction project can be found in the following link:
Phase I Construction FAQs

 If you have questions regarding the construction of this project, please contact Michelle Quinney, Special Projects Manager, at (408) 827-3552 or MQuinney@LosGatosCA.gov
 
Please click on the following links for additional information regarding the Broadway and Bachman Avenue construction project:
• Resident/Business Owner meeting agenda – April 24th and 25th, 2016
• Resident/Business Owner presentation slides – April 24th and 25th, 2016
• Resident/Business Owner meeting – door hangers – April 11, 2016
• Resident/Business Owner meeting letter – April 11, 2016
• Town Council award of contract – February 16, 2016

Almond Grove Project Phase I Design Information


Please click on the following links for information related to the design of the Almond Grove Project.

If you have questions regarding the design of the Almond Grove Project, please contact Lisa Petersen, Town Engineer, at (408) 399-5773 or LPetersen@LosGatosCA.gov

Almond Grove Phase I - Plans, Specifications & RFP
Please note that the Plans and Specifications shown below are for information only and should not be used for bidding purposes.

Project #13-31 Almond Grove Street Reconstruction Phase I (Asphalt) 

Project #13-31 Almond Grove Street Reconstruction Phase I (Concrete) 

Design Update on Almond Grove Phase II - Remaining 8 streets

 
Following the Town Council’s approval of the Wilsey-Ham contract on April 19th for the design of the remaining eight concrete Almond Grove streets, which include Tait, Bayview, Glen Ridge, Almendra, Wilder, Bean, Massol, and Nicholson, the design work is now underway.
  
Upcoming field work related to the design is noted below:

 Wilsey-Ham will start locating and marking utilities on the streets during the week of May 9, 2016.  The utility locator will mark the existing utility locations in paint on the street or hardscape as well as use small flags to locate utilities in the planter strip landscaping.  This work is anticipated to take just over a month.

 Additionally, the consultant’s surveyor will begin to develop topographic surveys of the streets around the same time the utility locating and marking begins. This will entail a two person crew using tripod mounted equipment to collect this survey data.  Cones and/or flaggers may be used as necessary for traffic control but traffic impact will be minimal.  This work is anticipated to be completed by the end of June.

 Finally, during this same time period, a geotechnical investigation will be underway.  The geotechnical team will collect core samples of the existing concrete pavements using drill rigs powered by generators, which may be noisy but the work is anticipated to take only a few days.

 To stay informed of the latest updates regarding the project, visit the Town’s website at www.losgatosca.gov/AlmondGroveProject and subscribe to the “Notify Me” service on the left hand side of the project page.  Any questions regarding the project design can be referred to the Town Engineer, Lisa Petersen, at (408) 399-5773 or lpetersen@losgatosca.gov.

Almond Grove Request for Proposals 

Proposals Received


  

Revised Proposals Received

Almond Grove Project Costs
 
Ordinances Related to Almond Grove Historic District